DCM developed a campus masterplan and prototype building design. The masterplan provided for 7 new buildings between 63,000 and 125,000 SF of new construction on a 26- acre site.

The masterplan was approved by City Planning based on proposed sustainable and mitigation measures.

Phase I implementation of the masterplan includes a 121,600 SF single-story concrete tilt-up building

The program includes warm shell building for future build-out of Data Center white space including associated spaces for 24 MW of electrical infrastructure, Switchgear, UPS rooms, as well as office and common spaces.

The building exterior is planned as a highly insulated metal cladding rain screen system.